1400 Soil nails were installed on this project. There is 3000m² of Shot crete wall that is held entirely by soil nails.
The dead line for these walls were critical, as they were to enable 355,000m³ of excavation before the wet winter months. Ancor Loc completed the project on time, which was considered un-achievable by others.